E4 Group OGK-2 has sent proposals to resolve the conflict over breach of contract for construction of two units in Stavropol TPP.
According to the first version of the proposal, E4 and OGK-2 to sign a new contract for the construction of one unit on the Stavropol and Serovskaya Power Plant, where the WGC-2 plans to begin construction. These facilities would be supplied equipment already ordered E4 from Siemens for 2 blocks of the Stavropol TPP. The remaining funds E4 Group is ready to set off against the advance of the newly concluded contracts. The total amount of the new contract will be calculated on the basis of the basic cost parameters for the Stavropol TPP. The final contract price will depend on the additional costs of new construction. At the same time costs associated with the transfer of construction of one of the blocks from Stavropol in Serov, invited to share in OGK-2. In this case, E4 Group is prepared to pay OGK-2 12% per annum from the received advance - from receipt of funds prior to the suspension of the contract, said in a press release the group.
Under the second option, OGK-2 will have to compensate E4 3,5% of the amount of the contract. OGK-2 will also have to return the advance, less the costs incurred by E4. Engineering company generating companies to sell equipment previously ordered from Siemens, for 206 million euros. This amount includes the supply, installation and warranty service and does not include bonuses and agency fees to the cost of equipment and services. These conditions are fully consistent with the terms of the contract general contractor, who voted for the Chairman of the Board of Directors of OGK-2 Denis Fedorov, who was at the time of the commission on investments in the Board of Directors of RAO UES of Russia (December 2007).
However, OAO WGC-2 does not agree to the proposals Group E4. According to the press service of the company, 7 billion rubles have to go back to the accounts of WGC-2, that is part of the advance - 5.5 billion rubles and interest - 1.5 billion rubles.
E4 Group and the WGC-2 in late 2007 signed a contract for investment projects in Stavropol TPP, the contractor was paid an advance (8.8 billion rubles), but in April 2009, the generating companies agreed to terminate the contract and the money -- return. disputing parties reached the courts.
13 October 2009 the Arbitration Court of Stavropol region invalidated the decision of OAO WGC-2 on the termination of the contract with JSC E4 Group. The court also dismissed the counterclaim WGC-2 to the E4 Group on the refund of $ 8.8 billion.
Overview of the oil market for 15.10.09
Bank of America recorded a loss on the results of III quarter, said the first positive signs
NBU: the Law on the financing of Euro 2012 appealed to the Constitutional Court
Perhaps refinance problematic COP will Oschadbank
In the case of correction for the upcoming week shares of the telecommunications sector may be the most interesting ideas
Index of the Frankfurt Stock Exchange Xetra DAX fell 0.64%, the index of the London Stock Exchange Futsi 100 fell 0.48%
Trading volume on the MICEX derivatives market amounted to 604.66 million rubles
Gazprombank in 1 half of 2009 reduced net profit under IFRS by 24% to 24.4 billion rubles
Failed, and the second attempt to break resistance at 1.4960